Project Plans:
Requires free Autodesk Express Viewer Cover Site Plan Floor Plan Demolition Sections Building Sections Foundation Plan |
Burlingame A Toilet - Rebuild Public Restroom Facility Location: Burlingame State Park; Charlestown, RI Contractor: A. Autiello Construction Co., Inc. Construction/Renovation Cost: $148,000 Completion Date: March 2003 Project: Gut the entire interior of the building. Install new plumbing drain, waste and vent system, new concrete slabs sloped to drain, new plumbing fixtures including showers, and new toilet partitions. Add one new shower to the womens' side of the building. Provide universal access into the building by regrading the entrances and modifying the entrance screen wall to provide the proper wheelchair turning radius. Contact person: Lisa T. Lawless, PE, 222-2776 ext. 4312 ![]() |
|